San
Antonio Area Freeway System
Proposed
Tollway
System |
|
This page
last updated December 7, 2020 |
Beginning
in the
late 1990s and early 2000s, state officials began to realize that their
traditional "pay-as-you-go" approach to
funding to build new roads was no longer able to keep pace with the
state's highway needs. A combination of increased population, a surge
in interstate and international trade, a sudden dramatic increase in
construction
costs starting in late 2002, and the increasing cumulative effects of inflation on
the state's
static fuel tax, which was last adjusted in 1991, were taking a toll
(no pun intended) on highway revenues. Additionally,
improved fuel mileage, which translates into
less
fuel tax
paid
per mile driven, as well as the legislature's diversions of funds from
the
state's Highway Fund to pay
for non-transportation budget shortfalls, were
also substantially cutting into the amount of funding available for
transportation. Furthermore, the
federal fuel tax, having
not been adjusted itself since 1993, was
also suffering from inflation-induced depreciation. As a
result, the
federal government in 2008 and 2009 was forced to rescind previously
allocated funding to the states due to those shortfalls in expected
revenue. Texas and San
Antonio have historically been
shortchanged on transportation funding, so there was already a substantial backlog of
needed
projects from all those years of being shortchanged on top of the demands caused by recent explosive population and
traffic growth. To top it all off, until recently, the state's funding issues
had
only been addressed by the Legislature through a series of
small band-aid
measures, and Congress to this day continues to struggle to fix transportation
funding issues on the national level even after promises by the current
administration to aggressively address infrastructure funding.
This all created
a "perfect storm" resulting in a crisis in highway funding that started
coming to a head in the first few years of the new millennium. To
help stave off a complete funding collapse without increasing taxes,
the legislature and voters approved bonding and tolling to pay for new
roadways in 2001. To help back some of that new debt with a sustainable
revenue source, the Texas Transportation Commission in 2003 directed
that all freeway projects be evaluated for toll
worthiness
and be constructed as toll projects if they were deemed viable.
This included several projects in the works in San Antonio at that time including US 281 and Loop 1604. Additionally, the state encouraged regional authorities in the early
2000s to develop local funding
mechanisms to help augment state funds. To that
end, Bexar County leaders in 2003 created the Alamo Regional Mobility
Authority (ARMA) to take a local leadership role in finding funding
solutions for the San Antonio area. Because there are
few local
transportation
funding options available under state law, the primary focus was on
using tolls as
the backing for bonds that would fund major projects. Tolling
the new roadways and lanes would provide the funding mechanism
to pay for them in lieu of waiting for limited
tax-based financing, and this was the approach taken by both the state and other RMAs statewide. It was
projected that using
this
financing method would allow many major projects to be built
as soon as 25 years ahead of the traditional
gas
tax-funded schedules and, as a result, also substantially
cheaper. However, although created primarily as a tolling agency, ARMA
has actually been able to secure non-toll funding sources for all of
the
projects it has developed,
most notably the US 281/Loop 1604 interchange, which was
originally expected to be
a toll project. ARMA today continues to develop other non-toll projects, mostly on county roads.
During
its sessions in 2013 and 2015, the Texas Legislature
approved new
funding sources for
highways. These changes allocate a percentage of sales taxes
and motor vehicle sales taxes as well as oil and gas production taxes
annually to the state highway fund. The legislation also ended
most
of the budget diversions from the highway fund. The increases in
funding from these changes have
allowed the removal of tolling from all previously-planned local
toll projects.
As
a footnote to all this, it is often asserted by toll road opponents that
voters never approved tolling roads in Texas. However, in 2001, voters
overwhelmingly approved Proposition 15,
which authorized the state to borrow money to build highways, including
toll roads, which was clearly stated in the ballot language. It could
be argued that voters did not understand the extent to which the state
would use tolling, but given that toll projects are mentioned three
times in the ballot language ("turnpikes, toll roads, toll bridges"),
it should have been evident to voters that toll projects were going to
be a major outcome of approving this proposition. The referendum did
not require approval from voters for specific projects, only approval
by the Texas Transportation Commission. As
there are currently no more active toll projects planned for San
Antonio, this page now describes the history of local toll proposals.
On this page:
Types of tollways
Some
people have the perception that implementing a
tollway on a road means adding tolls to
an existing
roadway. However, this is not possible under state law. So in all
cases, toll road projects involve the construction of new lanes on
existing roads or completely new roads, both of which almost
always consist of expressway lanes. Below are the
different types
of tollways that have been considered for Bexar County.
- Tolled
expressway mainlanes
In this scenario, the mainlanes of the
expressway, which are all new, are tolled, while the access
roads remain
toll-free. The expressway lanes include overpasses at major
intersections (i.e. no traffic signals.) It is
important
to
understand that in every case where this type of tollway has been
proposed,
it was essentially the same proposal as a non-tolled
version of the same project would have been. The
only
difference is
that
drivers who opt to use the new expressway lanes pay a
toll. The existing toll-free, signalized lanes remain
toll-free
and serve as the frontage roads for the new expressway lanes. This is a
more "traditional" type of tollway
such the Sam
Houston Tollway (Beltway 8) in Houston or George Bush Turnpike in
Dallas. This type of tollway was planned for part of US 281
but
dropped when new funding became available in 2015. It had
been studied for the Kelly Parkway, a possible future extension of
SH 151 outside of Loop 1604, for
Wurzbach Parkway between
Blanco and Wetmore, and for a section of Bandera Rd., but those
proposals
were subsequently dropped.
- Managed
lanes
In this type of project, on roads that
already have non-tolled
expressway lanes,
those existing lanes remain toll-free, but new tolled express
lanes known as "managed lanes" (see definition below) are built in the
median between the
existing toll-free expressway lanes or, in some cases elevated
over or depressed below the
existing lanes. The
existing lanes may
have
to be moved or reconfigured to provide sufficient room for
the new lanes. When built at-grade, the managed lanes are
separated from
the
toll-free lanes by barriers with limited entry and exit
points to the
toll-free lanes. Examples
of this type
of tollway are I-10 West
(Katy Freeway) in Houston and the North Tarrant Express in Ft.
Worth. This
type of tollway was planned for part of US 281 but dropped when new
funding became available in 2015. Elevated
tolled managed lanes were also proposed for I-35 North but were dropped
in mid-2018 and the new elevated lanes will now consist of toll-free
general purpose lanes and HOV lanes. Managed
lanes have also
been
proposed at times for parts
of I-10 West, I-10 East, Loop
1604, SH 151, and I-37.

Cross-section of freeway with managed lanes
NOTE
Number
of lanes can vary depending on project.
Diagrams are
for illustrative
purposes only and are not to
scale.

What is a managed lane?
A
managed lane
is a lane where the operational strategies of the
lane are adjusted in real-time to ensure that the lane
remains
free-flowing, thus providing for a guaranteed travel time for users of
the lane. For example, toll rates or vehicle occupancy
requirements may fluctuate based on
traffic
conditions or time of day. Typically, managed lanes
allow
toll-free access for buses, carpools, and emergency vehicles while
single-occupancy vehicles (i.e. solo drivers) can use the lane by
paying a variable-rate toll.
How
is this beneficial? Besides providing a clear way for public
transportation and emergency vehicles and encouraging carpooling, it
also gives solo commuters who want
or need to get where they're going faster an opportunity to
bypass congestion by paying a toll to use any excess capacity
of
the lane. Every motorist who opts to do so removes one more vehicle
from
the toll-free lanes which can help ease congestion. The
resulting toll revenue
helps to subsidize for the road, saving scarce tax dollars for other
needed
projects.
|
-
Tolled
interchange
In this plan, new direct-connect ramps
between intersecting roadways (tolled or toll-free) are
tolled.
Tolled interchanges are currently proposed as part of the Loop 1604
managed lanes project. Tolled interchanges were also planned as part of
a managed lane project on I-35 North, but that project has since had
its toll component dropped. A tolled interchange at US 281
and
Wurzbach Parkway was
studied but determined to be infeasible. Other tolled
interchanges were previously proposed at Loop 1604 and SH 151,
Loop 1604 at
I-10 East, and on the planned Kelly Parkway at I-35 and at Loop 410.
The US 281/Loop 1604 interchange was initially planned as a
tolled interchange but various other funding sources allowed
it to
be built with non-tolled connectors instead.
Proposed toll
systems
2009 Plan
In
2009,
ARMA identified a number of feasible tollway projects in Bexar
County. An initial "starter system" of about 20 miles along
US 281 and Loop 1604 was
originally identified with additional segments of Loop 1604
subsequently added. Several other possible toll projects had
also
been investigated by TxDOT but were subsequently determined to be
infeasible. The map below shows the proposed
tollway locations in San Antonio in that 2009 plan.

STARTER
SYSTEM
- US 281 North
from Loop 1604 to the Comal County line
- Loop 1604
northern arc from Military Dr. West to I-10 East and its interchanges
with SH 151, I-10
West, US 281 North, I-35 North, and I-10 East
FUTURE
PROPOSED ADDITIONS
- I-35 from
Loop 410 South to the Comal County line
- SH 151 from
Loop 1604 to SH 211
- I-10 West
from Loop 1604 to Boerne
- I-10 East
from Loop 410 to SH 130 in Seguin
- Kelly
Parkway and its interchanges with I-35 South and Loop 410
INFEASIBLE
SECTIONS
(These
sections had previously been considered for tolling but were
subsequently determined to not be feasible.)
- SH 16
(Bandera Rd.) from Loop 410 to Loop 1604
- Wurzbach
Parkway from Starcrest Dr. to Blanco Rd.
- Interchange
at Wurzbach Parkway and US 281
- Southern
half of US 281/Loop 1604 interchange
(funded instead as
a toll-free project using
federal
economic stimulus funds)
2014 Plan
In the years between 2009 and 2014, ARMA and TxDOT continued studies on
the various corridors and made revisions to their list of possible
toll projects. In December 2014, the MPO incorporated the
latest proposals into their plans as shown on the map below.

CARRIED-OVER
FROM 2009 PLAN
- US 281 North
from Loop 1604 to the Comal County line
- Loop 1604
northern arc from US 90 West to I-10 East including tolled
ramps at I-10
West, I-35 North, and I-10 East
- I-10 East
from Loop 410 to SH 130 in Seguin
- I-35 from downtown to FM 1103 (the managed lanes
along this section would mostly be double-decked)
- I-10 West
from Loop 1604 to Boerne (this would be built in two phases with the
first phase from Loop 1604 to Leon Springs)
NEW
ADDITIONS
- SH 151 from
Loop 410 to Loop 1604
- I-37 from SE Military to Fair Ave.
DELETED
SECTIONS
(These
sections were
dropped from consideration for tolling.)
- Kelly Parkway
- SH 151 outside of Loop 1604
- I-35 from US 281 to Loop 410 South
- Loop 410 between I-35 North and I-10 East
- Tolled ramps to US 281 north of Loop 1604
Tolls
& toll collection
In
late 2007, the MPO approved toll
rates of 17 cents per mile and 57 cents per tolled interchange ramp for
most passenger vehicles. Larger vehicles (such as
18-wheelers)
would pay 46 cents per mile and $1.15 per ramp. As was the emerging trend
at that time, all tolls were planned to be collected
electronically; there would be no tollbooths. In fact, the US 281
project in San Antonio appeared to be the first in Texas that proposed
to use all-electronic tolling. In electronic tolling,
tolls are collected using an electronic
transponder ("toll tag"). These tags are stickers mounted
inside the
windshield of the vehicle that contain a radio frequency ID (RFID) chip
that transmits the tag's unique code when triggered by electronic tag
readers located at strategic locations along
the toll system. These readers then record the identifier codes of tags
as they
pass by and the toll is deducted from a pre-paid
balance
in the
account associated with tag. Alternatively, vehicles can use
the toll system without toll tags; in this case, the license plates of these
vehicles are photographed and the vehicle owner billed by mail for the
toll
amount
plus
an
additional collection fee.
The
toll tag
systems across the state are interconnected, so toll tags from any
Texas toll agency can be used on any tollway in the state. In addition,
Texas' toll tag system is interoperable with several other states.
Current status
After
the increases in state highway funding in 2013 and 2015, full funding was secured to
build the US 281 North
and I-10 West expansions without tolls.
The
SH 151, I-10 East, and I-37 segments of the 2014 plan were also subsequently switched to
non-toll funding sources.
That
left
the I-35 North and Loop 1604 (Bandera Rd. to I-35) expansions as
the last remaining local toll projects. After further evaluation of
expected revenue, the diminished economy of scale of the remaining projects due to
the lack of a larger toll system, and a push by state leaders starting in
late 2017 to
deprecate tolling, local officials decided in 2018 to nix the remaining
local toll plans, first for I-35 North, and then Loop 1604. This
completed the dismantling of the local toll plans.
Cibolo Parkway
Separate
and unrelated to the above plans, the Cibolo city council
instructed city staff in 2015 to investigate
options to extend FM 1103 south to FM 78 and I-10 and a blue-ribbon
citizens committee was formed to study the matter. In 2016, that
committee recommended the project go forward as a tollway. This project
is independent of the plans above and has no involvement from TxDOT or
ARMA. More information on that project is here.
History
As
mentioned in the introduction on this page, numerous issues in the late
1990s and early 2000s resulted in severe funding shortages for
highways.
As state and local officials sought new methods for
funding, tolling emerged as the primary new tool. Plans
to create local toll roads got underway in 2003, first with the
creation of the Alamo Regional Mobility Authority (ARMA), and then when
the Texas Transportation Commission (TTC)
ordered that "controlled-access
mobility projects in any
phase of development or construction must be evaluated for
tolling. This includes new-location facilities and increased
capacity projects such as adding additional main lanes or constructing
new main lanes." (TTC Minute Order 109519,
12/18/03) The order specifically included "increased capacity projects
such as...constructing new main lanes." These
two events kickstarted the local effort to create a regional
toll-funded transportation plan.
"Starter system" is born
In late
2003, TxDOT was working to secure additional funding for a planned
expansion
of US 281 from Loop 1604 to Stone Oak Pkwy. Because that
project
fit the requirements of the 2003 TTC order, TxDOT was compelled to evaluate
it for
possible tolling. That review showed that it was viable for tolling, so
per the TTC's order, the project was
reclassified as a toll project. A plan to expand
Loop 1604
was also evaluated for tolling and subsequently combined with the US
281 project to form a tollway "starter system" plan.
Cintra-Zachary proposal
Initially,
the
plan was that TxDOT would build the starter system beginning
in late
2005, then transfer operational responsibility to ARMA when completed
around 2009. But in mid 2005, Cintra-Zachary, the private
consortium selected to build the first leg of the now-defunct
Trans-Texas
Corridor,
made an unsolicited bid to build and operate the San Antonio tollway
starter system. After review, TxDOT decided that the proposal
had
enough merit that it would have to be considered, and in accordance
with state law, accepted other bids for the
starter system. According to media reports, Cintra-Zachary's
bid
would
allow the project to be built faster, would pay the state a concession
fee in return for a 50-year lease to collect the tolls, and because it
was privately funded, would allow TxDOT to
reallocate the $600 million that it would have used to build the
starter system to other projects. After a bit of rancorous
debate
between TxDOT and ARMA, it was agreed that the Cintra-Zachary bid
would be accepted with local input.
Opposition builds; first lawsuit
After
word of the
toll projects became public, a substantial amount of grassroots
opposition, headed by the Texas Toll Party group who had also
vehemently opposed Austin area toll projects, started to
form. They showed en masse at an MPO meeting in mid
2005
and managed
to get the proposed Loop 1604 West project tabled, at least for the
time
being. As one might imagine, these events added some
uncertainty
to the entire project. However, TxDOT awarded the
construction
contract for the US 281 project from Sonterra to Stone Oak in
September 2005 and preparation work for construction began in December
2005. After workers hit sewer line in early 2006, opponents seized on
that opportunity to file a lawsuit
challenging the project, arguing that it required a full (and costly)
environmental impact statement (EIS) instead of the numerous
less-comprehensive
environmental assessments (EA) that had been performed up to that
time. Federal law only requires an EIS to be performed if an
EA
finds significant impacts, which the EAs for 281 had not. However,
TxDOT and the Federal Highway Administration (FHWA), who were
both named in the suit, jointly agreed in January 2006 to suspend work
on the 281 project, as well as a separate overpass planned at
281 and Borgfeld, so that a consolidated EA for
the
entire corridor could
be done and categorical determination
made of whether a full impact
statement would need to be performed.
US 281 plan moves forward
In
early 2007,
the new EA for 281 was completed and released. As with previous
assessments, it
found no substantial issues, a so-called "Finding of No Significant
Impacts" (FONSI). The FHWA reviewed and approved the EA in August
2007. TxDOT announced plans to cancel the overpass
project at Borgfeld as ARMA indicated it was now intending to expand
281 from 1604 to Borgfeld as a single project with
construction possibly beginning in 2008.
Other toll project considered
ARMA
also
completed studies for other possible toll projects on I-35
North,
Bandera Road, and Wurzbach Parkway. In early 2007, ARMA
determined that the Wurzbach Pkwy. proposal was not feasible for
tolling, and the tolling option for the Bandera Rd. project was
dropped by the MPO board in October 2009.
TxDOT
announced
in mid-2006 that it was considering possible toll lanes along I-10 West
from Loop 1604 to Boerne and on I-10 East from Loop 410 to
Seguin. Those would be new managed lanes in the median; the
existing
lanes would remain toll-free. Subsequent proposals for the
I-10 West
project adjusted the northern endpoint-- at least for a first
phase-- to Leon Springs.
Statewide moratorium passed; ARMA
takes over
On
June 11th,
2007, after a series of discussions with the Legislature, Governor
Perry signed compromise legislation that put a two-year moratorium on
the construction of privately financed toll roads and allowed local
mobility authorities the right of first refusal on all toll projects
within their jurisdiction. The bill
included a number of exceptions, mostly in the Dallas-Fort Worth and
Houston areas; the 281 and 1604 toll projects in San Antonio were
not exempted. Consequently, on June 15th, ARMA voted to
assume
control of those
projects with plans to fund the projects with toll-backed bonds and
to begin
construction in mid 2008.
Loop 1604 study
In
late June
2007, TxDOT released the results of the EA for the Loop 1604 managed
lanes
and expansion and previewed the plans for the proposed improvements.
That EA
also had a FONSI outcome. However, given the history of legal
challenges on the 281 project and expectation of similar litigation for
1604, ARMA decided to move forward with a full EIS
for Loop 1604 anyway. That study subsequently experienced a number of
scope
revisions
and funding challenges that substantially delayed it.
US 281 project finalized
In
December 2007,
the MPO approved the toll rates for the US 281 project. ARMA
announced that they would build the 281 project in two segments: Loop
1604 to Marshall Rd. and Marshall Rd. to the Comal county
line. Construction on the first segment, from Loop 1604 to Marshall,
was
expected to start in mid 2008 with completion in late 2010. The
second segment was expected to be completed in 2012.
Second
lawsuit filed
In February
2008, toll opponents and environmentalists once again filed a lawsuit
challenging the second 281 EA. After
initial arguments, the judge ruled that the plaintiffs' case had
sufficient standing to move forward with discovery. During
the
discovery process, TxDOT announced that they found a document that had
been inadvertently
omitted from the administrative record for the EA
and asked for a 60 day stay to allow time to submit the
document to the FHWA for review to determine if it would affect the
overall findings of the study. In early October 2008, TxDOT
then
reported that they had uncovered a conflict of interest with the
contractor who had performed the endangered species portion of the
study. Specifically, it was discovered that a TxDOT staff biologist was
married to an employee of the company hired to do the a portion of the
study. It was further discovered that the TxDOT employee's
supervisor was aware of the situation and allowed it but that controls
put in place to mitigate the conflict were not enforced. Although
it was determined that this likely had no impact on the results of the
study, TxDOT asked the FHWA to revoke their environmental approval for
the project to preempt the inevitable legal battle.
Subsequently, the defendants (TxDOT, ARMA, and the FHWA)
agreed
to do a full environmental impact statement (EIS) for the
corridor and the lawsuit was dismissed as moot in November
2008. In April 2009, ARMA hired the consultant to conduct the new EIS.
ARMA hires consortium
In the
meantime, while the legal challenges had been working their way through
the system,
ARMA had hired Cibolo Creek
Infrastructure Joint Venture in May 2008 to design and build the 281
project. The consortium was headed by Fluor Enterprises of
Irving, Texas, and Balfour Beatty Infrastructure Inc. of Atlanta, and
included several San Antonio subcontractors. (Contrary to
pervasive public
perception, this consortium-- unlike the previous Cintra-Zachary
group--
included no foreign companies.) Design work was 30% completed when it
was stopped in late 2008 due to
the aforementioned litigation and subsequent decision to do a full
EIS. ARMA had planned to start construction in late 2008 or
early
2009 on the first segment, from Loop 1604 to Marshall Rd., with
estimated completion in late 2010. However, those plans were
scrapped pending a new project to be recommended by the
environmental impact statement process.
Additions
to
tollway system plan
In
December 2014, the MPO approved an updated toll plan that included the
previously-planned managed lanes on US 281 North and Loop 1604 as well
as newly-proposed managed lanes on I-35 from downtown to FM
1103, I-10 West from Loop 1604 to Boerne, I-10 East from Loop
410
to SH 130, SH 151 from Loop 410 to Loop 1604, and I-37 from SE Military
to Fair Ave.
281/1604
southern interchange built
During
the
Great
Recession, Congress approved a national economic "stimulus"
plan that poured additional federal money into
road construction
projects. In
February
2009, the Metropolitan Planning Organization (MPO)
approved allocating San
Antonio's share of the largesse to be used in conjunction with matching
state funding for the first half of a
281/1604
interchange. This project built all four of the ramps
connecting
1604
to 281 inside the loop, i.e. northbound 281 to both directions
of 1604, and both directions of 1604 to southbound 281. The
use
of the federal funds allowed the ramps to be toll-free. The
Texas Transportation Commission (TTC) approved the state's share on
March 5th, 2009. Construction began in early 2011 was
completed in mid 2013. It was
determined that the ramps connecting to 281 north of 1604 could not be
built until the lingering issues stemming from the lawsuits and
associated
environmental studies for 281 north of 1604 were resolved. However,
funding was identified for those ramps
so
that construction could begin as soon as the legal and environmental
issues were resolved.
New
managed lanes plan for US 281
In
May 2012, local officials announced they had identified funding to
expand US 281 from Loop 1604 to Stone
Oak
Pkwy with some toll-free lanes.
The working plan for US 281 included two to three
toll-free freeway
lanes in each direction and one or two tolled managed lanes. The
managed lanes would include direct access to a park and
ride
facility being planned for the corridor. It was
hoped
that
construction would begin sometime in 2014 or 2015 once the ongoing
environmental study of the corridor was complete and approved and
barring any further legal challenges.
Loop 1604 projects
Over on Loop 1604, plans were announced to build two toll-free
freeway lanes in each
direction from Braun to Potranco (essentially a southward
extension of the existing freeway
configuration at Bandera Rd.) once the ongoing environmental study was
complete, which was expected to be in 2015. Space would be left to
add managed
toll
lanes in the future that would connect the managed lanes being planned
north of Bandera Rd.
New
toll funding plan
In
January
2014, TxDOT and ARMA
announced funding had been secured
to expand US 281 from Loop 1604 all the way to Borgfeld Rd. using a mix
of
non-tolled and tolled/managed lanes. Some funding would come
from
traditional tax-funded sources with the remainder coming from
bonds backed by toll revenue. Funding was also
allocated-- mostly from a City of San Antonio bond issue--
to complete the northern ramps for the Loop 1604 interchange; as with
the
previously completed ramps in the interchange, these new ramps will
also be non-tolled.With
funding now in hand for the entire corridor,
construction was
expected to start in late 2015 or early 2016 contingent on the approval
of the environmental study that was scheduled to be complete in mid
2015. The funding for 281 was part of a larger financing
package
that included funds for proposed managed lanes on I-10 West from Loop
1604 to Ralph Fair Rd. and for non-tolled expressway lanes on Loop 1604
from SH 151 to US 90. In
the summer of 2015, TxDOT submitted and the FHWA approved the completed
EIS for the US 281 project.
Legislature approves new
funding sources In
2013, the legislature approved a new funding source for highways by
using revenue from gas and oil production taxes, which was subsequently
approved by voters. Then in 2015, the legislature approved additional
new funding from sales taxes and motor vehicle sales taxes. During
the summer of 2015, several local officials indicated that should
voters sign-off on the new financing and
the expected funding then be allocated by the state, efforts would be
made to remove
the toll component from the US 281 project. In early September
2015, the MPO approved a resolution to that effect and the TTC approved
the funding
change later that month. In November 2015, voters indeed approved the
funding proposition, and officials
announced shortly thereafter that the plans for 281 would be updated to
remove the toll component with an expected groundbreaking in
2017. The Loop 1604 and I-35 projects, because of their scope and
expense (nearly $1 billion each), would stay on the books as toll
projects.
Tolling depreciated
In
late 2017, the governor and lieutenant governor directed the
TTC to remove (or at least discourage) tolling
from future projects. However, because Loop
1604 and I-35 were
already in the local plans with toll bonding underpinning
their funding,
and because the new state funding for the area was still projected to
be insufficient to
cover their cost, they retained their designation as
toll projects; this is
required under federal regulations in order for planning on the projects to
continue.
Toll component removed from
remaining projects
In mid 2018, revised funding forecasts became
substantially more favorable. In light
of that, the MPO
determined it could remove tolling from the last local
projects that included it--
first I-35 North, and then finally Loop 1604, bringing a somewhat anti-climatic end to the tumultuous local toll road wars.
Other
sites of interest
|