Other San Antonio Area Roads
West Bexar Road Expansion Projects

This page last updated November 11, 2025

The far west side of Bexar County — the area outside Loop 1604 roughly between Bandera Rd. and the Medina River — is the fastest growing area in the county. As a result, there are several major road expansion projects underway or in the works. This page consolidates information that I know or can find about the various known projects from TxDOT, Bexar County, the City of San Antonio (COSA), the Alamo Regional Mobility Authority (ARMA), and developers.

Status info for TxDOT projects is current as of 11/11/25, Bexar County/ARMA projects as of 11/9/25, and COSA projects as of 11/8/25.



ADVERTISEMENT




West Bexar projects map

Base map from OpenStreetMap


UNDER CONSTRUCTION
MAP ID LOCATION AGENCY PROJECT DESCRIPTION ESTIMATED
COMPLETION
1
CULEBRA RD (FM 471)
Old FM 471 to SH 211
TxDOT Widen to four lanes with median or center turn lane and construct interchange at SH 211
(More details)
(SH 211 interchange)
Early 2027
(68% complete)
2
US 90
At SH 211
TxDOT Construct westbound to eastbound turnaround Mid 2026
(99% complete)
3
TALLEY RD
Wiseman Blvd to Tamaron Pass
Bexar County Widen to four-lane divided roadway
2027
(15% complete)
4
LOOP 1604
Bandera Rd to I‑10
TxDOT Widen to 10 lane freeway including two HOV lanes
(More details)
Late 2025
(98% complete)
5
SH 151
Loop 410 to Loop 1604
TxDOT Widen to six lanes
(More details)
Early 2027
(78% complete)
6
COUNTY RD 381 Developer Widen road
~2026
7
MONTGOMERY RD Bexar County Extend Montgomery Rd to meet Grosenbacher Rd
2026
(45% complete)
8
US 90
Loop 1604 to SH 211
TxDOT Widen to ten lanes and construct WB to NB flyover
(More details)
Mid 2029
(1% complete)
9
US 90
Loop 1604 to Montgomery Rd
TxDOT Add auxiliary lanes Mid 2026
(65% complete)
9
ALAMO RANCH PKWY/GALM RD Developer Extend roads Late 2026
ADVANCED PLANNING / SCHEDULED FOR CONSTRUCTION
MAP ID LOCATION AGENCY PROJECT DESCRIPTION ESTIMATED
START
A
FM 1560
Culebra Rd to Bandera Rd
TxDOT Widen to four lanes with median or center turn lane.
(More details)
(Schematic)
Mid 2026
B
BABCOCK RD
Hausman Rd to UTSA Blvd
COSA Widen to four lanes
(More details)
Early 2026
C
CULEBRA RD (FM 471)
At LOOP 1604
TxDOT Convert to a Diverging Diamond Interchange (DDI) TBD
D
SH 211
US 90 to Potranco Rd
TxDOT Expand road to four-lane divided highway TBD
E
GROSENBACHER RD
Potranco Rd to W Grosenbacher Rd
Bexar County Widen to four lanes 2028
F
CAGNON RD
Ponder Rd to
S of Medina River
Bexar County Realign road and build bridge over Medina River 2026
G
US 90
Loop 1604 to SH 211
TxDOT Upgrade to six lane freeway
(More details)
2027
H
MILITARY DR
Hunt Rd to
Reed Rd
COSA Widen to four-lane divided road
(More details)
Late 2025
I
US 90
Military Dr to Loop 410
TxDOT Operational improvements
(More details)
2032
J
LOOP 1604
US 90 to Macdona Locoste Rd
TxDOT Expand to four-lane divided highway with Restricted Crossing U‑turn (RCUT) intersections
(More details)
2026
K
ALAMO RANCH PKWY
Loop 1604 to Calaveras Way
ARMA Build four-lane parkway with overpasses in median of existing roadway
(More details)
2027
L
POTRANCO RD (FM 1957)
SH 211 to FM 471
TxDOT Widen road to six lanes
(This project is currently broken into two phases: SH 211 to CR 381, which has a current estimated start date of 2031, and CR 381 to FM 471, which has no start date at this time. A public meeting for this project is expected in 2026.)
TBD
M
ROFT RD
Culebra Rd to Rockwall Mill
Bexar County Upgrade from rural road to suburban road with curbs, drainage, and sidewalks Late 2025
N
TALLEY RD
Old Talley Rd to Tamaron Pass
Bexar County Widen road to four lanes and remove sharp bend Late 2026
O
MARBACH RD
Wentwood Rd to Just My Style
Bexar County Complete gap in corridor Late 2026
P
LOOP 1604
Bandera Rd to SH 151
TxDOT Expand freeway to six lanes TBD
Q
LOOP 410
Valley Hi Dr to Somerset Rd
TxDOT Expand freeway to eight lanes and construct new interchange at I-35 South TBD