The far west side of Bexar County — the area outside Loop 1604 roughly between Bandera Rd. and the Medina River — is the fastest growing area in the county. As a result, there are several major road expansion projects underway or in the works. This page consolidates information that I know or can find about the various known projects from TxDOT, Bexar County, the City of San Antonio (COSA), the Alamo Regional Mobility Authority (ARMA), and developers.
Status info for TxDOT projects is current as of 11/11/25, Bexar County/ARMA projects as of 11/9/25, and COSA projects as of 11/8/25.
|
ADVERTISEMENT |
| UNDER CONSTRUCTION | |||||
| MAP ID | LOCATION | AGENCY | PROJECT DESCRIPTION | ESTIMATED COMPLETION |
|
|
CULEBRA RD (FM 471) Old FM 471 to SH 211 |
TxDOT | Widen to four lanes with median or center turn lane and construct interchange at SH 211 (More details) (SH 211 interchange) |
Early 2027 (68% complete) |
|
|
US 90 At SH 211 |
TxDOT | Construct westbound to eastbound turnaround | Mid 2026 (99% complete) |
|
|
TALLEY RD Wiseman Blvd to Tamaron Pass |
Bexar County | Widen to four-lane divided roadway |
2027 (15% complete) |
|
|
LOOP 1604 Bandera Rd to I‑10 |
TxDOT | Widen to 10 lane freeway including two HOV lanes (More details) |
Late 2025 (98% complete) |
|
|
SH 151 Loop 410 to Loop 1604 |
TxDOT | Widen to six lanes (More details) |
Early 2027 (78% complete) |
|
|
COUNTY RD 381 | Developer | Widen road | ~2026 | |
|
MONTGOMERY RD | Bexar County | Extend Montgomery Rd to meet Grosenbacher Rd | 2026 (45% complete) |
|
|
US 90 Loop 1604 to SH 211 |
TxDOT | Widen to ten lanes and construct WB to NB flyover (More details) |
Mid 2029 (1% complete) |
|
|
US 90 Loop 1604 to Montgomery Rd |
TxDOT | Add auxiliary lanes | Mid 2026 (65% complete) |
|
|
ALAMO RANCH PKWY/GALM RD | Developer | Extend roads | Late 2026 |
|
| ADVANCED PLANNING / SCHEDULED FOR CONSTRUCTION | |||||
| MAP ID | LOCATION | AGENCY | PROJECT DESCRIPTION | ESTIMATED START |
|
|
FM 1560 Culebra Rd to Bandera Rd |
TxDOT | Widen to four lanes with median or center turn lane. (More details) (Schematic) |
Mid 2026 | |
|
BABCOCK RD Hausman Rd to UTSA Blvd |
COSA | Widen to four lanes (More details) |
Early 2026 | |
|
CULEBRA RD (FM 471) At LOOP 1604 |
TxDOT | Convert to a Diverging Diamond Interchange (DDI) | TBD | |
|
SH 211 US 90 to Potranco Rd |
TxDOT | Expand road to four-lane divided highway | TBD | |
|
GROSENBACHER RD Potranco Rd to W Grosenbacher Rd |
Bexar County | Widen to four lanes | 2028 | |
|
CAGNON RD Ponder Rd to S of Medina River |
Bexar County | Realign road and build bridge over Medina River | 2026 | |
|
US 90 Loop 1604 to SH 211 |
TxDOT | Upgrade to six lane freeway (More details) |
2027 | |
|
MILITARY DR Hunt Rd to Reed Rd |
COSA | Widen to four-lane divided road (More details) |
Late 2025 | |
|
US 90 Military Dr to Loop 410 |
TxDOT | Operational improvements (More details) |
2032 | |
|
LOOP 1604 US 90 to Macdona Locoste Rd |
TxDOT | Expand to four-lane divided highway with Restricted Crossing U‑turn (RCUT) intersections (More details) |
2026 | |
|
ALAMO RANCH PKWY Loop 1604 to Calaveras Way |
ARMA | Build four-lane parkway with overpasses in median of existing roadway (More details) |
2027 | |
|
POTRANCO RD (FM 1957) SH 211 to FM 471 |
TxDOT | Widen road to six lanes (This project is currently broken into two phases: SH 211 to CR 381, which has a current estimated start date of 2031, and CR 381 to FM 471, which has no start date at this time. A public meeting for this project is expected in 2026.) |
TBD | |
|
ROFT RD Culebra Rd to Rockwall Mill |
Bexar County | Upgrade from rural road to suburban road with curbs, drainage, and sidewalks | Late 2025 | |
|
TALLEY RD Old Talley Rd to Tamaron Pass |
Bexar County | Widen road to four lanes and remove sharp bend | Late 2026 | |
|
MARBACH RD Wentwood Rd to Just My Style |
Bexar County | Complete gap in corridor | Late 2026 | |
|
LOOP 1604 Bandera Rd to SH 151 |
TxDOT | Expand freeway to six lanes | TBD | |
|
LOOP 410 Valley Hi Dr to Somerset Rd |
TxDOT | Expand freeway to eight lanes and construct new interchange at I-35 South | TBD | |